Ticket 20140110_2

Ticket Number: 20140110_2Ticket State: CLOSED
Ticket Opened: 2014-01-10 12:42Ticket Closed: 2014-01-13 07:26
Ticket Description: Scheduled work on power infrastructure at PSI
Scheduled Starttime: 2014-01-11 07:00:00Scheduled Endtime: 2014-01-11 18:00:00

Problem Description:

PSI performs maintenance work on their electrical power installation.
In a first step the east part of the campus will be disconnected.
There is no guaranty the UPS is able to back up during the whole periode.
Most likely our router swiPS2 will loose power.

In a second step the west part of the campus will be disconnected.
There is no guaranty the UPS is able to back up during the whole periode.
Most likely our router swiPS1 will loose power.
At 18:00 latest, the work is expected to be accomplished.

Only the network access of PSI is affected by this event.
All other services of SWITCH are not affected.

Affected:

From 2014-01-11 07:00 until 2014-01-11 18:00
Impact: no impact
Service: network access
Sites: PSI


Actions:


2014-01-13 07:58
Our routers didn't shut down at all.
The UPS was able to backup during the periods of the loss of the main power supply.


For all questions about this ticket, please send mail to noc@switch.ch
or call +41 44 268 15 30.