Ticket 20180412_2

Ticket Number: 20180412_2Ticket State: CLOSED
Ticket Opened: 2018-04-12 16:31Ticket Closed: 2018-04-14 08:58
Ticket Description: Scheduled software upgrade swiBR1 and swiBR2
Scheduled Starttime: 2018-04-14 08:00:00Scheduled Endtime: 2018-04-14 09:00:00

Problem Description:

Due to security and bug fixes we will upgrade the software of our router swiBR1 and swiBR2 on Saturday, April 14th between 8:00 and 9:00. This will be done sequentially and will take around 20 minutes per router.
IP and OPN access of FFHS Brig should continue to operate normally due to redundancy.
No outage is expected.

Affected:

From 2018-04-14 08:00 until 2018-04-14 09:00
Impact: no more redundancy
Service: P2P/OPN
Sites: FFHSRD-FFHSBR


From 2018-04-14 08:00 until 2018-04-14 09:00
Impact: no more redundancy
Service: network access
Sites: FFHS Brig

Actions:


2018-04-14 08:47
swiBR2 back online

2018-04-14 08:30
swiBR2 reload for upgrade

2018-04-14 08:17
swiBR1 back online

2018-04-14 08:00
swiBR1 reload for upgrade


For all questions about this ticket, please send mail to noc@switch.ch