SWITCHlan Trouble Tickets

Transparency is very important to us. We therefore publish all trouble tickets about issues that have an impact on our customers. We show both currently open tickets as well as all closed tickets.

Ticket 20090113_3

Ticket Number: 20090113_3Ticket State: CLOSED
Ticket Opened: 2009-01-13 14:00Ticket Closed: 2009-01-28 14:44
Ticket Description: Scheduled Utility Power Upgrade at Equinix ZH1
Scheduled Starttime: Scheduled Endtime:

Problem Description:

On January 17, 2009, Equinix plans to install new utility power cables and power distribution units in its datacenter ZH1 (Z├╝rich Hardstrasse 235).

During the upgrade, the datacenter will be disconnected from external power and powered exclusively by Diesel generators. No downtime of our routers swiIX1 and swiIX2 is expected, but their electrical power supply, like for all our peers and upstream providers, is at risk during the maintenance.


From 2009-01-17 06:30 until 2009-01-17 20:00
Impact: no impact


2009-01-17 00:00
The maintenance was smoothly performed and the location has been switched back to on utility power supply. The generator backup was working well during the whole maintenance and there was no incidents on our routers.

For all questions about this ticket, please send mail to noc@switch.ch
or call +41 44 268 15 30.