SWITCHlan Trouble Tickets

Transparency is very important to us. We therefore publish all trouble tickets about issues that have an impact on our customers. We show both currently open tickets as well as all closed tickets.

Ticket 20190212_4

Ticket Number: 20190212_4Ticket State: OPEN
Ticket Opened: 2019-02-12 10:50Ticket Closed:
Ticket Description: Scheduled cable maintenance in Horw on April 9, 2019
Scheduled Starttime: 2019-04-09 07:30:00Scheduled Endtime: 2019-04-09 11:30:00

Problem Description:

Zentralbahn is moving its cable infrastructure into a new building at Horw railway station. The fiber access cable to HSLU's campus at Technikumstrasse 21 will be cut and re-spliced in the morning of April 9, 2019. Thanks to redundant paths, both SWITCHlan and HSLU networks are not expected to lose services during the intervention.

Affected:

From 2019-04-09 07:30 until 2019-04-09 11:30
Impact: no more redundancy
Service: network access
Sites: HSLU, UNILU


From 2019-04-09 07:30 until 2019-04-09 11:30
Impact: Total loss of connectivity
Service: darkfiber
Sites: Horw_Luzern


From 2019-04-09 07:30 until 2019-04-09 11:30
Impact: no more redundancy
Service: P2P/OPN
Sites: EmpaEawag-KAS, HSLU-LZ-AG, UNIBE-HFSJGJFJ-be2-jfj2



For all questions about this ticket, please send mail to noc@switch.ch