Ticket Number: 20191216_1Ticket State: CLOSED
Ticket Opened: 2019-12-16 13:16Ticket Closed: 2020-01-22 15:26
Ticket Description: Scheduled maintenance on GEANT transatlanic link NYC-PAR
Scheduled Starttime: 2020-01-23 00:00:00Scheduled Endtime: 2020-01-23 06:00:00

Problem Description:

GEANT has announced a planned maintenance of their circuit provider of the NYC-PAR transatlantic circuit.
An outage is expected, however the entire window is reserved.

GEANT ticket 2019121634001803

All times are swiss local time (CET) unless otherwise mentioned.

Affected:

From 2020-01-23 00:00 until 2020-01-23 06:00 (CET)
Impact: Total loss of connectivity
Service: P2P/OPN
Sites: RKAU-SANTACLARA, SYNGENTA-INTERNET2


Actions:


2020-01-22 15:27
Apparently, the maintenance was performed a day earlier than scheduled and is now over.
(See GEANT ticket 2020012134002712)
Thus, there might have been outages today between 00:00 and 06:00.
Closing Ticket.