SWITCHlan Trouble Tickets

Transparency is very important to us. We therefore publish all trouble tickets about issues that have an impact on our customers. We show both currently open tickets as well as all closed tickets.

Ticket 20210910_1

Ticket Number: 20210910_1Ticket State: CLOSED
Ticket Opened: 2021-09-10 13:31Ticket Closed: 2021-10-08 15:51
Ticket Description: Scheduled router upgrade at PoP ZHDK/Toni (30.09.2021)
Scheduled Starttime: 2021-09-30 09:00:00Scheduled Endtime: 2021-09-30 14:00:00

Problem Description:

During this maintenance services on the router swiTO2 will be moved to the new 100G router swiTO1. Each service / link will be interrupted for a short time (some minutes) during migration.

Affected:

From 2021-09-30 10:00 until 2021-09-30 14:00
Impact: Total loss of connectivity
Service: network access
Sites: SZH


From 2021-09-30 10:00 until 2021-09-30 12:00
Impact: no more redundancy
Service: network access
Sites: ZHAW


Actions:


2021-09-30 14:00
All production links and services have been moved to the new router swiTO1. Some issues with Scion experimental services will addressed in a later maintenance window

2021-09-15 13:40
The work has been postponed due to unforeseen circumstances. A new maintenance window will be announced


All times are in local Swiss time CET / CEST.
For all questions about this ticket, please send mail to noc@switch.ch
or call +41 44 268 15 30.