Ticket Number: | 20230905_1 | Ticket State: | OPEN | ||
---|---|---|---|---|---|
Ticket Opened: | 2023-09-05 09:30 | Ticket Closed: | |||
Ticket Description: | Scheduled Fiber Maintenance UPC - Eawag-HSLU (29.09.2023) | ||||
Scheduled Starttime: | 2023-09-29 00:01:00 | Scheduled Endtime: | 2023-09-29 06:00:00 |
Problem Description:
Due to construction work by third parties (construction work/excavation work on Reblaubenweg 12.), a Sunrise fiber optic cable must also be rerouted. This will result in an interruption of the link between Eawag and HSLU. SwitchLAN services will be rerouted to alternative paths, so no service affected is expected.Affected:
From 2023-09-29 00:01 until 2023-09-29 06:00Impact: no more redundancy
Service: P2P/OPN
Sites: EmpaEawag-KAS
From 2023-09-29 00:01 until 2023-09-29 06:00
Impact: no more redundancy
Service: network access
Sites: HSLU
All times are in local Swiss time CET / CEST.
For all questions about this ticket, please send mail to noc@switch.ch
or call +41 44 268 15 30.